Timetable of Deliverables and Milestones

  Preparation for Production

Timetable of Deliverables and Milestones

September 7, 2015
This is the timetable for the Deliverables and the Milestones as defined by the plan for EISCAT_3D: Preparation for Production. Other important dates in the project are also added to the timetable. A Deliverable represents a verifiable output of the project. They are denoted by Dx.y in the timetable below, where x is the number of the relevant Work Package and y is the number of the Deliverable within that Work Package. A Milestone is a control point where decisions are needed with regard to the continuation of the project. They are denoted by Mz in the timetable below, where z is the ordering number of the particular Milestone within the full project.

September 2015
Kick-off and technical meeting (M1) [OK]
Manufacturing Consultant Contractor contract signed (M2) [OK]
February 2016
First version of the data management plan (D2.1) [OK]
Technical report on approaches for sub-array beam-former (D3.1) [OK]

April 2016
Contracts signed with vendors (M3) [OK]

August 2016
End of first reporting period [OK]

November 2016
Site preparation complete (M4) [OK]

January 2017
First report on industry contracts (D4.1) [OK]

February 2017
Test plan for the Test Subarray (D2.2) [OK]

April 2017
Site preparation drawings delivered; antenna elements, structure and instrument container subsystems arrives at test site (M5) [OK]

June 2017
Front end, beam former and pulse and steering control subsystems arrives at test site (M6) [OK]
Software interface control documents (D5.1) [OK]

Project Review

July 2017
Second report on industry contracts (D4.2) [OK]

August 2017
Tendering documents, including standards and necessary supporting documentation (D2.3) [OK]
Test Subarray testing report (D6.1) [OK]
End of second reporting period
End of project