Timetable of Deliverables and Milestones
September 7, 2015
This is the timetable for the Deliverables and the Milestones as defined by the plan for EISCAT_3D: Preparation for Production. Other important dates in the project are also added to the timetable. A Deliverable represents a verifiable output of the project. They are denoted by Dx.y in the timetable below, where x is the number of the relevant Work Package and y is the number of the Deliverable within that Work Package. A Milestone is a control point where decisions are needed with regard to the continuation of the project. They are denoted by Mz in the timetable below, where z is the ordering number of the particular Milestone within the full project.
September 2015
Kick-off and technical meeting (M1) [OK]
Manufacturing Consultant Contractor contract signed (M2) [OK]
February 2016
First version of the data management plan (D2.1) [OK]
Technical report on approaches for sub-array beam-former (D3.1) [OK]
April 2016
Contracts signed with vendors (M3) [OK]
August 2016
End of first reporting period [OK]
November 2016
Site preparation complete (M4) [OK]
January 2017
First report on industry contracts (D4.1) [OK]
February 2017
Test plan for the Test Subarray (D2.2) [OK]
April 2017
Site preparation drawings delivered; antenna elements, structure and instrument container subsystems arrives at test site (M5) [OK]
June 2017
Front end, beam former and pulse and steering control subsystems arrives at test site (M6) [OK]
Software interface control documents (D5.1) [OK]
Project Review
July 2017
Second report on industry contracts (D4.2) [OK]
August 2017
Tendering documents, including standards and necessary supporting documentation (D2.3) [OK]
Test Subarray testing report (D6.1) [OK]
End of second reporting period
End of project