The Skibotn ground works have now started
![](https://eiscat.se/wp-content/uploads/2019/06/E3DS1-A1-outrigger-road-1.jpg)
May 2019: Ground works (photo: ONOS)
Our contractor, ONOS Ole Nordmo & Sønn AS, has now started preparing the EISCAT_3D Skibotn site for use. First tasks are to build a road to three of the outrigers (NW1, NW2 and NW3) and to prepare the ground for all 10 outriggers. The work then continues with preparing the main site itself