We have now received the final first articles needed for the Production and Engineering Test (PET) system.
Earlier this week we received the two first articles of the Pulse and Steering Control Unit. This means that we can start the full hardware integration tests of the PET system.
Above: the transmitter rack showing three of the first article transmit units (part of Sub-Array Transmitter delivery) and the, now delivered, two first article transmitter control units (part of the Pulse and Steering Control Unit delivery). The first article receiver (part of the First Stage Receiver Unit delivery) is located in a separate rack.