2020-01-29: Q&A session reopened for BUILDINGS related questions


Question 187:  It is required that the facade on both the building and garage should be plated. What is the reason (we are normally offering pine wood)?
Answer 187: The requirement is to reduce the expected maintenance need of the facades.


2020-02-14: Q&A session for BUILDINGS related questions closed